Planning and Approvals

A comprehensive assessment process

Before the project can be constructed, it must undergo a rigorous planning and environmental assessment process. Specialist studies are being undertaken to assess:

  • Biodiversity/ Ecology

  • Fire and hazard risk

  • Landscape and visual impact

  • Traffic and transport

  • Noise

  • Aboriginal Cultural heritage

  • European heritage

  • Hydrology and stormwater

  • Agriculture

These assessments will inform the concept design and support a planning permit application, that is expected to be lodged in October 2026. The Project will require other approvals, including for grid connection. The project team is committed to ensuring the proposal considers, addresses and mitigates relevant considerations and risks.

Environmental significance

The site sits within the Green Wedge Zone, is partly covered by an Environmental Significance Overlay.

We take these considerations seriously and are committed to rigorous environmental assessment, transparent reporting, and design measures that protect existing environmental values.

The project has been designed to minimise impacts on the environment as far as possible. Any unavoidable native vegetation impacts will need to be offset under the Victorian vegetation offset scheme.

Fire

The Middle Hut BESS site is located outside the CFA Bushfire Management Overlay. This was one of several factors considered in selecting the site.

A Fire Safety Study is being prepared in response to the CFA's Design Guidelines and Model Requirements for Renewable Energy Facilities, following discussions with the CFA. The CFA will review the study and advise the Department of Transport and Planning whether there are any conditions they would like to impose on the project.